Project Details
Location | : Dhofar Governorate |
End User | : Rural Areas Electricity Company (RAECO) and Abu Dhabi Future Energy Company (Masdar) |
Client | : TSK Group |
Type Of Contract | : Subcontract |
Brief Scope of work | : 1. Excavation,33 kV Cable & Fiber Optics cable laying to loop Wind Generator Towers with each other and to connect them to Substation and Installation of Wind Generator Transformers – 13 nos. & Installation of Terminations, earthing etc., Testing and Commissioning. 2. Construction of 132kV Double Circuit Over Head line. |
Start Date | : 12;05;2018 |
Completion Date | : 15.07.2019 |
SALIENT FEATURES
No of Incomers | : 4 [Muladah & Al Filaj] |
No of outgoings | : 33kV GIS – 18 bays |
Busbar Configuration | : Double Busbar configuration |
LILO | : 60.00 Meters |
No of Towers | : 2 |
132kV | : GIS 10 bays |
132kV Power Transformer | : 125 MVA |
33kV Switchgear | : AIS (20 bays) |
Earthing Transformer | : 315 KVA |
Capacitor Banks | : 20 MVAR |
Control & Relay panels | : 26 Nos |
SCMS | : 1204 IO Points |
RTU | : 1826 IO Points |
HV AC Rating | : 132kV – 2 x 345kW; 33kV – 2 x 248kW |
Gantry Structure | : Double circuit gantry for 4 feeders -YEW |
Man-hours without LTI | : 562,500 |
Peak Workforce | : 165 Nos |
Sub Station Building Size | : 132kV Building – 1056 sq mtr; 33kV Building – 868 sq mtr. |