Project Details
Location | : Al Khadra |
End User | : Mazoon Electricity Co. S.A.O.C |
Client | : Mazoon Electricity Co. S.A.O.C |
Type Of Contract | : Main Contract |
Brief Scope of work | : Construction of 8 nos. 33KV Outgoing Feeders from Al Khadra Grid Station & Construction of 33KV Feeders & 11KV Feeders |
Start Date | : 31/01/2017 |
Completion Date | : 09/06/2018 |
SALIENT FEATURES
33KV Over Headline | : 20Kms Panther Conductor |
33KV UG cable | : 47Km, 33KV 3Cx300sqmm cable |
11KV Over Headline | : Nil |
11KV UG cable | : 73Km, 11KV 3Cx240sqmm cable |
No. of Poles | : 220 No. |
Horizontal Directional Drilling | : 3800 Mtrs. |
33KV Onload Disconnector | : 47 Nos. |
11KV onload Disconnector | : 7 Nos. |
RMU/OLU | : 32/31 Nos. |
Man-hours without LTI | : 182,300 hours |
Peak workforce | : 108 people |
Substation building size | : 7mx 5m Outdoor Distribution S/S – 24 Nos. |
Duration | : 10 months |