CONSTRICTION OF NEW 132/11KV PRIMARY SUBSTATION WORK AT OSOOL POULTRY FARM.

Inspiration comes of working every day.
Location : Osool
End User : Osool Poultry S.A.O.C
Client : Osool Poultry S.A.O.C
Type Of Contract : Main Contract
Brief Scope of work

: Construction of New 132/11kV Primary Substation work at Osool

Poultry and associated OHL of 45KM from Sayala Production station.

Start Date : 11/10/2021
Completion Date : 07/11/2022 
No of Incomers : 2 NoS. 11KV Feeder
No of outgoings : 8 Nos. 11KV Feeder
Busbar Configuration : 132/11kV 
Over Headline : 45 Kms of 132KV AAAC ELM Conductor
11KV Switchgear : 16 Panels AIS
132/11KV Power Tx : 31.5 MVA -1 Nos.
132KV Switchgear : 1 Bay 25KA/3Sec with 2500A