2×6 Mva Ibra Rop Primary Substation (33kv/11kv) With 33kv Incomer Feeders

2×6 Mva Ibra Rop Primary Substation

(33kv/11kv) With 33kv Incomer Feeders

Project Details

Location: Ibri
End User: Mazoon Electricity Co. S.A.O.C
Client: Mazoon Electricity Co. S.A.O.C
Type Of Contract: Main Contract
Brief Scope of work: Construction Of 2x6 Mva Ibra Rop Primary Substation (33kv/11kv) With 33kv Incomer Feeders.
Salient Features: Executed the works in accordance with Tender Specification [TB-37/2012]
Start Date: 16/10/2016
Completion Date: 27/08/2017

SALIENT FEATURES

No of Incomers: 1 No. 33KV Feeder
No of outgoings: 4 Nos. 11KV Feeder
Busbar Configuration: Outdoor Gantry With Tubular Busbar.
Underground cable: 4.6 Km of 33KV 3Cx 300sq.mm. Cable
33/11.5KV Power Tx: 6MVA -2 Nos.
33KV Onload Disconnector: 5 Nos.
11KV Capacitor Banks: 3 MVAR – 2 Nos.
33KV Auto Recloser: 2 Nos.
11KV Auto Recloser: 4 Nos.
RTU: 1 No. (I/O Signals- 280)
Man-hours without LTI: 54,434 hours
Peak workforce: 57 people
Substation building size: 50mx50m Boundary wall Plot
Duration: 10 Months

Related

8 nos. 33KV Outgoing Feeders from Al Khadra Grid Station & Construction

Distribution / Projects

CONSTRICTION OF NEW 132/11KV PRIMARY SUBSTATION WORK AT OSOOL POULTRY FARM.

Projects / Solutions

Dhofar Wind Farm

Projects / Renewable Energy

Construction of 2x20MVA (Hay Al Turath & Al Afiyah PSS) And Upgrading of IZZ PSS to 2x20MVA At Al Dakhiliyah Governorate

Distribution / Projects