132/33kV Bedyah Grid Station

132/33kV Bedyah Grid Station.

Loop In and Loop Out from existing 132kV OHL Mudhairib 32/33kV GS – Al Kamil

Project Details

Tender Number: TB 34/2016
Location: Bedyah
End User: Oman Electricity Transmission Company S.A.O.C
Client: Oman Electricity Transmission Company S.A.O.C
Type Of Contract: Main Contract
Brief Scope of work: Supply, Installation, Testing & Commissioning of 132/33 KV GIS Substation and associated 132 kV LILO at Madinat Barka and Al Khadra
Salient Features: Design, supply, construction, installation, testing and commissioning of Transmission portion of 132/33kV GIS Grid Station. Existing double circuit Mudhairib 132/33kV GS – Al Kamil 132kV OHL circuits shall be Loop In and Loop out at Badyah 132/32kV Grid Station.
Start Date: 26.01.2017
Completion Date: 03.12.2018

SALIENT FEATURES

No of Incomers : 4 (Mudhairib – 1 & Mudhairib – 2; Al Kamil – 1 & Al Kamil – 2)
No of outgoings : 33kV I/C – 4 Nos
Busbar Configuration: Double Busbar configuration-encapsulated R-Y-B
LILO: 45 Meters
No of Towers: 2
132kV GIS : 8 bays
132kV Power Transformer : 125 MVA
Earthing Transformer : 750 KVA
Control & Relay panels: 8 Nos
SCMS : 1086 IO Points
HV AC Rating : 2 x 82.7kW; 2 x 142.9kW
Gantry Structure : Double circuit gantry for 4 feeders -YEW
Man-hours without LTI : 473580
Peak Workforce : 150
Sub Station Building Size : 745 sq. mtr

Related

New Grid Station at Madinat Barka and Al Khadra

Projects / Transmissions

8 nos. 33KV Outgoing Feeders from Al Khadra Grid Station & Construction

Distribution / Projects

2x6 Mva Ibra Rop Primary Substation (33kv/11kv) With 33kv Incomer Feeders

Distribution / Projects

New Grid Station at Jebreen

Projects / Transmissions